Government building renovation: BIM model, 4D simulation and quantity take-off

Project data
- Location
- Saudi Arabia
- Services
- BIM modelling, coordination, 4D scheduling, quantities (5D)
- Model covers
- Existing building, items to be demolished and new construction
Project requirements
The renovation requires one model that brings together the existing building, the items to be demolished and the new construction, with a detailed programme and the quantities.
Our scope of work
We model the existing condition, the items to be demolished and the new construction, and coordinate them. We then prepare a Level 4 schedule, link it to the model for a 4D simulation of the works, and take off the quantities from the model.
Deliverables
- BIM model of the existing building, the items to be demolished and the new construction
- Level 4 schedule
- 4D simulation linked to the schedule
- Quantity take-off from the model (5D)